The major projects report 2011 PDF Download

Are you looking for read ebook online? Search for your book and save it on your Kindle device, PC, phones or tablets. Download The major projects report 2011 PDF full book. Access full book title The major projects report 2011 by Great Britain: National Audit Office. Download full books in PDF and EPUB format.

The major projects report 2011

The major projects report 2011 PDF Author: Great Britain: National Audit Office
Publisher: The Stationery Office
ISBN: 9780102976793
Category : Political Science
Languages : en
Pages : 328

Book Description
This is a companion volume to the main report (HC 1520-I, ISBN 9780102976786)

The major projects report 2011

The major projects report 2011 PDF Author: Great Britain: National Audit Office
Publisher: The Stationery Office
ISBN: 9780102976793
Category : Political Science
Languages : en
Pages : 328

Book Description
This is a companion volume to the main report (HC 1520-I, ISBN 9780102976786)

The major projects report 2011

The major projects report 2011 PDF Author: Great Britain: National Audit Office
Publisher: The Stationery Office
ISBN: 9780102976786
Category : Technology & Engineering
Languages : en
Pages : 78

Book Description
Action taken by the Ministry of Defence to balance its overall budget in the short term following the Strategic Defence and Security Review has contributed to a near £500 million in-year cost increase in the 15 largest defence projects. When coupled with previous cost growth, these projects are now £6 billion above forecasts made when the main investment decisions were taken. For the third successive year, central planning decisions taken by the Department, including delaying various projects, have had the biggest impact on cost growth, accounting for £237 million of the increase. Of this, £113 million relates to decisions to enhance capability. Macro-economic factors, such as adverse foreign exchange rates, accounted for £176 million of the increase. Cost overruns from project-specific technical issues accounted for £53 million. During 2010-11, there was a total increase of 30 months (with an average two months per project) in the forecast time to complete these projects and bring them into service. This brings the total delay on all 15 projects to 26.8 years. Long-term cost analysis by the NAO has shown that the difference between the approved and forecast costs of all projects which have had their main investment decision approved since 2000 is £10.6 billion (an 11.4 per cent increase). Additional costs have been avoided by reducing the amount of equipment the Department originally planned to buy. Had the Department not reduced equipment numbers, cost growth could have been between £18.2 billion and £19.4 billion (approximately 20 per cent) above the approved costs.

The Major Projects Report 2012

The Major Projects Report 2012 PDF Author: Great Britain: National Audit Office
Publisher: The Stationery Office
ISBN: 9780102980585
Category : Technology & Engineering
Languages : en
Pages : 78

Book Description
In respect of its largest defence projects there are early signs that the Ministry of Defence has begun to make realistic trade-offs between cost, time, technical requirements and the amount of equipment to be purchased. Nevertheless, the continuing variances to cost and time show the MOD needs to do consistently better. This report, which gives a progress review of the 16 largest defence projects, shows that in the last year there has been a total forecast slippage of 139 months and increase in costs of £468 million. This means that, since the projects were approved, costs have increased by £6.6 billion (around 12 per cent more than the planned cost) and the projects have been delayed by 468 months, taking almost a third longer than originally expected. It would be unrealistic to expect MOD and industry to identify every risk at the start of technically challenging projects. However, the continuing problems indicate that MOD has more to learn from historic. The MOD is accepting the capability risk and some wider costs resulting from these project delays and is having to make difficult decisions about long-term capabilities. The MOD has made a significant investment in new and upgraded helicopters to address the shortfall identified in the NAO's 2004 report. The MOD has also spent £787 million on air transport and air-to-air refuelling aircraft to support current operations and address capability gaps, such as those caused by the previously reported delays to the A400M transport aircraft. However, capability gaps remain

The Major Projects Report 2009

The Major Projects Report 2009 PDF Author: Great Britain. National Audit Office
Publisher: The Stationery Office
ISBN: 9780102963380
Category : Political Science
Languages : en
Pages : 340

Book Description
This is a companion volume to the main report (HCP 85-I, ISBN 9780102963342)

The major projects report 2010

The major projects report 2010 PDF Author: Great Britain: National Audit Office
Publisher: The Stationery Office
ISBN: 9780102965513
Category : Political Science
Languages : en
Pages : 302

Book Description
This is a companion volume to the main report (HC 489-I, ISBN 9780102965506)

Ministry of Defence

Ministry of Defence PDF Author: Great Britain: Parliament: House of Commons: Committee of Public Accounts
Publisher: The Stationery Office
ISBN: 9780215041661
Category : Technology & Engineering
Languages : en
Pages : 56

Book Description
The Ministry of Defence (the Department) continues to struggle with managing its equipment programme on an affordable basis, resulting in the cancellation or deferral of major projects and a damaging impact on value for money. In 2010-11 the forecast costs to complete the 15 largest defence projects increased by £466 million. Since their original approvals the estimated costs of these 15 projects have increased by £6.1 billion and now stand at approximately £60 billion (an 11.4% increase). In aggregate these 15 projects are forecast to be completed 322 months later than originally planned. Projects approved since 2002 show significantly lower cost growth than those approved before this date, which is encouraging. Now the Department faces unpalatable decisions. Decisions to cancel or slow projects and to reduce equipment numbers have added significant long-term costs to the whole defence programme and to unit costs within the programme. Capability has been affected and this has all resulted in poor value for money. Large defence equipment projects have contributed disproportionately to overall cost growth. In the past, the Department has repeatedly failed to challenge unrealistically low estimates for the largest and most complex equipment projects from suppliers. The Department is still unable to set out openly the extent of the gap between income and expenditure it still faces, and how and by when any shortfall will be resolved. The report notes little progress in reducing the turnover of the Senior Responsible Owners (SROs), who oversee individual projects.

Major Projects Report 2008

Major Projects Report 2008 PDF Author: Great Britain. National Audit Office
Publisher: The Stationery Office
ISBN: 9780102954425
Category : Technology & Engineering
Languages : en
Pages : 36

Book Description
The Major Projects Report 2007 covers cost, time and performance data for military equipment projects in the year ended 31 March 2008. 20 of the largest projects are examined where the main investment decision has been taken by the Ministry of Defence (the MoD) along with ten projects still in the Assessment Phase. Six projects are new to this report: future lynx; modernised target acquisition designation sight/pilots night vision sensor; naval extrememly high frequency/super high frequency satellite communication terminals; Typhoon future capability programme; advanced jet trainer project and project Eagle

2011-12 Major Projects Report

2011-12 Major Projects Report PDF Author: Australian National Audit Office
Publisher:
ISBN: 9780642812858
Category : Defence contracts
Languages : en
Pages : 600

Book Description
This fifth Major Projects Report (MPR) continues the review by the Australian National Audit Office (ANAO) of selected major Defence equipment acquisition projects (Major Projects). It builds on the earlier work by the Defence Materiel Organisation (DMO) and the ANAO to improve the transparency of, and accountability for, the status of Major Projects for the benefit of the Parliament, the Government and other stakeholders. Acquiring and sustaining capability for the Australian Defence Force is critically important work and this report provides an update on 29 of the most significant projects being managed by the DMO. The extent of reporting on Major Projects by the DMO reflects positively on the organisation and the Ministers for Defence and Defence Materiel in their pursuit of better acquisition outcomes.

Sessional Returns

Sessional Returns PDF Author: Great Britain: Parliament: House of Commons
Publisher: The Stationery Office
ISBN: 9780215048387
Category : Political Science
Languages : en
Pages : 442

Book Description
On cover and title page: House, committees of the whole House, general committees and select committees

Major projects report 2007

Major projects report 2007 PDF Author: Great Britain: National Audit Office
Publisher: The Stationery Office
ISBN: 9780102951486
Category : History
Languages : en
Pages : 40

Book Description
The Major Projects Report 2007 covers cost, time and performance data for military equipment projects in the year ended 31 March 2007. 20 of the largest projects are examined where the main investment decision has been taken by the Ministry of Defence (the MoD), along with ten projects still in the Assessment Phase. Overall the MoD is in a similar position to 2006 for forecast cost and performance, but there continue to be time delays. The current total forecast cost for the 20 largest projects is £28 billion, which is £2.5 billion over the 'most likely' budget when the main investment decision was taken. The MoD expects ten projects to deliver within their most likely budgeted cost. Most of this cost growth occurred in earlier years but, on two projects, the Type 45 Destroyer (£354 million) and the Astute Class Submarine (£142 million), there has been significant cost growth in-year. The MoD has now agreed revised contracts on both of these projects to incentivise industry to reduce costs. The MoD was again pro-active in limiting potential in-year cost increases on individual projects through reassessing requirements, reducing quantities of equipments and re-allocating expenditure to other projects or budget lines. Five projects were delayed by a total of an extra 38 months this year. Of these, the most significant were the Type 45 Destroyer which has been delayed by a further 11 months and the Terrier and Next Generation Light Anti-Armour Weapon projects have each been delayed by a further 12 months. Detailed Summary Sheets for each of the 30 Projects are in Volume 2 (HCP 98-II, ISBN 9780102951493). There have been significant developments of interest on a project that appeared in the Major Projects Report until 2002-03, the Landing Ship Dock (Auxiliary) project, and detailed findings are given in Volume 3 (HCP 98-III, ISBN 9780102951509).